Welcome to CHIRON Intranet

 
 

ACTION LIST

Task 1.4

DELAY

ALL PARTNERS (excepted ASDIS and Ragnhild from SU-DE)
Till the 13th of January 2006 all partners (excepted ASDIS and Ragnhild from SU-DE) send the final and edited version of their communication presented at the Paris Workshop according to the established Template.

RECALL : According to the Paris meeting, it should have been done up to the 21st of October 2005 !


 

Tasks 1.5

SU-DE
Till the 03rd of March 2006 SU-DE confirms date and place of the Third CHIRON Coordination and Working Meeting and provide information about stay and organisation of this meeting.

According to the open discussion in Paris, this third meeting should take place in Stockholm (Sweden) from 19 June 2006 (Afternoon) to 21 June 2006 (Morning).

EDEN / SU-DE
Till the 03rd of March 2006 EDEN (in close collaboration with SU-DE) confirms date and place of the Third CHIRON Open Workshop and provide information about stay and organisation of this workshop (papers submission, ...).

According to the open discussion in Paris, the Third CHIRON Open Workshop should be held within the framework of the EDEN 2006 Annual Conference which will take place in Vienna (Austria) from 14 June 2006 to 17 June 2006.

 


Task 4.2


SU-DE
Till the 06th of February 2006 SU-DE sends suggestions (Table of Content Draft, ...) to all partners in order to achieve the task.

ALL PARTNERS
Till the 17th of February 2006
all partners send feedback to SU-DE in shape of written and signed comments.



Task 5.2

DELAY

EDUWEB
Till the 06th of January 2006 EDUWEB sends a Table of Content to all partners.

RECALL : According to the Paris meeting, it should have been done up to the 09th of December 2005 !

ALL PARTNERS
Till the 13th of January 2006 all partners send feedback to EDUWEB.

RECALL : According to the Paris meeting, it should have been done up to the 23rd of December 2005 !

EDUWEB
Till the 20th of January 2006
EDUWEB sends the final version of the Table of Content to all partners.

RECALL : According to the Paris meeting, it should be done up to the 13th of January 2006 !

ALL PARTNERS
Till the 03rd of March 2006
all partners send their contributions to EDUWEB.

EDUWEB
Till the 17th of March 2006
EDUWEB sends the first draft of the survey to all partners.

ALL PARTNERS
Till the 31st of March 2006
all partners send feedback to EDUWEB.

EDUWEB
Till the 21st of April 2006
EDUWEB sends the final version of the survey and an extended summary to all partners.



Task 6.1

DELAY

EDEN
Till the 06th of January 2006 EDEN sends EU benchmark documents relevant for u-learning to all partners.

RECALL : According to the Paris meeting, it should have been done up to the 09th of December 2005 !

MSH
Till the 20th of January 2006
MSH sends suggestions to all partners.

RECALL : According to the Paris meeting, it should be done up to the 13th of January 2006 !

ALL PARTNERS
Till the 27th of January 2006
all partners send feedback to MSH.

RECALL : According to the Paris meeting, it should be done up to the 20th of January 2006 !



Task 6.2

EDEN
Till the 10th of February 2006 EDEN sends scheme proposal to all partners.

EDEN
Till the 10th of February 2006 EDEN sends questionnaire proposal to all partners.

ALL PARTNERS
Till the 17th of February 2006 all partners send feedback to EDEN.

EDEN
Till the 24th of February 2006
EDEN publishes the questionnaire.

ALL PARTNERS / EDEN
Till the 31st of March 2006 EDEN collects the filled-in questionnaires.

EDEN
Till the 21st of April 2006 EDEN sends the first draft of the survey to all partners.

ALL PARTNERS
Till the 28th of April 2006 all partners send feedback to EDEN.

EDEN
Till the 05th of May 2006 EDEN sends the final version of the survey and an extended summary to all partners.



 

 

This project has been funded with support from the European Commission.
This publication reflects the views only of the author, and the Commission cannot be held responsible
for any use which may be made of the information contained therein.

CHIRON Content Manager