   Task 6.2    
EDEN
Till the 10th of February 2006 EDEN sends scheme proposal to all partners.
EDEN
Till the 10th of February 2006 EDEN sends questionnaire proposal to all partners.
ALL PARTNERS
Till the 17th of February 2006 all partners send feedback to EDEN.
EDEN
Till the 24th of February 2006 EDEN
publishes the questionnaire.
ALL PARTNERS / EDEN
Till the 31st of March 2006 EDEN collects the filled-in questionnaires.
EDEN
Till the 21st of April 2006 EDEN sends the first draft of the survey to all partners.
ALL PARTNERS
Till the 28th of April 2006 all partners send feedback to EDEN.
EDEN
Till the 05th of May 2006 EDEN sends
the final version of the survey and an extended summary to all partners.
             
|